Emerson Expressway Rehabilitation
Concrete Pavement and Approach Slab Rehabilitation:
Thriebeam Installation:
Milling and Resurfacing:
Pavement Markings:
Project Challenges and Accelerated Schedule
One of the key challenges faced during this project was the need to complete extensive concrete work under two separate 9-day full detours. The tight timeline required careful coordination, strategic planning, and effective use of resources to ensure that work was completed safely and efficiently within the allotted timeframe. This was part of an accelerated project schedule designed to minimize disruption to traffic and complete the work as quickly as possible.
Despite the complexity of the project, the original contract duration of 400 days was completed in just 100 days, with a total of 300 days saved. This achievement was a testament to the project's excellent planning, execution, and management, all of which contributed to reducing road closures and delays while maintaining high standards of safety and quality.
Outcome and Conclusion
The completion of the Emerson Expressway rehabilitation project ahead of schedule resulted in improved traffic flow, enhanced safety features, and a longer-lasting road surface. By delivering the project 300 days early, significant cost savings were achieved, and the local community benefited from reduced disruptions to their daily commute. The collaborative effort between FDOT, contractors, and the community was essential to the successful outcome of the project.
In summary, the Emerson Expressway from Beach Blvd to Hart Expressway rehabilitation project, with a budget of $11 million, successfully upgraded critical infrastructure in Duval County. With a combination of technical expertise, efficient project management, and a commitment to quality, the project was delivered successfully, improving road safety, functionality, and longevity.